Fairfield Church of Christ, Fairfield
- Type of Project: Addition to existing church
- Duration of Project: 20 months including value-engineering
- Square footage: 29,587 sf
- Partners: Derek Howard, DH Architects
- Noteworthy Comment: Extensive value-engineering to reduce costs after bid award. Features Octagon tower.
Germantown United Methodist Church, Germantown
- Type of Project: Heavy timber construction with wind bent frames
- Duration of Project: 5+ years design, development and fund raising. 12 month construction.
- Square footage: 19,605 sf with walk-out lower level fellowship hall
- Partners: Alan Scherr, Architect
- Noteworthy Comment: Lead architect transition during design stage. Vancon was asked to stay on the design team.
Mt. Calvary Missionary Baptist Church, Dayton
- Type of Project: Multi-phased renovation to repurpose theatre to worship facility
- Duration of Project: 5 projects over 8-year period
- Square footage: 9,000 + sf
- Partners: Church leadership
- Noteworthy Comment: Vancon has completed multiple phases of work renovating an abandoned theatre into a beautiful worship and fellowship facility.
Pleasant Green Missionary Baptist Church, Trotwood
- Type of Project: Design/build new construction of pre-engineered metal building
- Duration of Project: 10 months
- Square footage: 9,400 sf + 1,900 sf finished balcony and enclosed canopy between existing and new facilities
- Partners: Church leadership
- Noteworthy Comment: Limited budget. Worked hand-in-hand with church leadership to provide the most value for their $1.1 mil budget.
Sacred Heart Catholic Church, New Carlisle
- Type of Project: New wood-framed construction
- Duration of Project: 14 months
- Square footage: 7,167 sf
- Partners: Father Bidwell
- Noteworthy Comment: Value-engineering, provided 23 voluntary alternates for consideration as means to reduce cost.
St. Christopher’s Catholic Church, Vandalia
- Type of Project: Structural metal
- Duration of Project: 12 months
- Square footage: 20,000 sf
- Partners: Church building committee
- Noteworthy Comment: Project lead to being awarded the St. Christopher Elementary School building project.